Just-in-Time: Quick answers
- Is One-Piece Flow Always Better?
Flow is always better than batch production or stagnation — that is foundational in TPS. But the question conflates flow with one-piece flow and one-piece flow with the whole of JIT. Flow (nagareka) is one principle alongside takt time, pull, and leveling. The real distinction is between one-piece flow (ideal state) and small-lot production (current-state reality).
- Is Takt Time a KPI, and What Does It Measure?
Takt time is not a KPI. It is a design constraint — the pace you design the work to, derived from customer demand divided by available time. It is one of three elements of standardized work and a key piece of Just-in-Time production.
- Does Toyota Do Value Stream Mapping?
Toyota does not draw LEI-style value stream maps or train them internally. But Toyota developed MIFA — the practice value stream mapping is based on — and a small number of specialists still use it.
- Value Stream Mapping vs Process Mapping
Process mapping records activities as a flowchart. Value stream mapping diagrams material and information flows from order to delivery. Toyota modified process mapping into MIFA; LEI renamed it value stream mapping.
Glossary
- Just-in-Time
One of the two pillars of the Toyota Production System — the principle of making only what is needed, when it is needed, in the amount needed, by synchronizing every process to the rate of customer demand.
- Pull System
A production control method where downstream processes withdraw only what they need from upstream processes, using consumption as the signal to replenish — the opposite of forecast-driven push production.
- Takt Time
The rate of customer demand expressed as a time interval — how often the customer needs one unit. Takt time is the heartbeat of a lean production system, synchronizing every process to the pace of actual demand.
- Cycle Time
The actual measured time required to complete one cycle of an operation — either the operator's complete work sequence or the machine's automatic processing time. Cycle time is observed and measured, not calculated from demand.
- Lead Time
The total elapsed time from the initiation of a process to its completion — typically from customer order to delivery, or from raw material entry to finished goods shipment. Lead time is the customer-facing measure of how responsive a production system is.
- Flow
The continuous movement of work through a production process without stoppages, batching, or waiting — the ideal state of JIT where each unit moves directly from one value-adding step to the next.
- One-Piece Flow
The ideal state of flow production where each unit is processed and passed to the next operation one at a time, with no batching or WIP accumulation between steps.
- Heijunka
The practice of leveling both the volume and mix of production over a fixed period of time, creating a predictable and repeatable pattern that absorbs demand variation without passing it upstream to suppliers and internal processes.
- Kanban
A physical card or signal that authorizes the production or movement of a specific part in a specific quantity — the operational mechanism that makes Just-in-Time possible on the shop floor.
- Production Instruction Kanban
A specific type of kanban card that authorizes a process to produce a defined quantity of a specific part — the "make" signal in Toyota's pull system, as distinct from the withdrawal kanban that authorizes movement.
- Withdrawal Kanban
A specific type of kanban card that authorizes the movement of parts from a supermarket or upstream process to a downstream process — the "move" signal in Toyota's pull system, as distinct from the production instruction kanban.
- Signal Kanban
A triangular-shaped kanban used for batch processes (such as stamping or molding) where one-piece flow is not feasible — it signals the process to produce a batch when inventory in the supermarket drops to a calculated reorder point.
- Supermarket
A controlled inventory buffer between two processes where each item has a defined location and quantity — the downstream process withdraws what it needs, and the withdrawal triggers replenishment from the upstream process, implementing pull at the point where continuous flow is not possible.
- Mizusumashi
A dedicated material delivery person who follows a fixed route on a timed cycle, supplying parts and materials to production operators so they never have to leave their stations — named after the water beetle that moves quickly across the surface.
- SMED
A systematic method for reducing equipment changeover time to single-digit minutes (under 10 minutes) — enabling smaller production lot sizes, more frequent changeovers, and greater production flexibility.
- Value Stream Map
A visual diagram that maps the complete flow of material and information from supplier to customer for a product family — showing every process step, inventory point, information flow, and time delay to reveal where waste exists and where improvement should focus.
- Material and Information Flow Analysis
Toyota's original method for diagramming the complete flow of materials and information through a production system — the practice that was later popularized outside Toyota as "value stream mapping" by the Lean Enterprise Institute.